Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf
Regular or Supplemental RCA: Regular
Type of Request: Contract - Award
Project ID (if applicable): 220201
Vendor/Entity Legal Name (if applicable): R Construction Civil, LLC dba R Construction Company
MWDBE Contracted Goal (if applicable): 19.00%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to R Construction Civil, LLC dba R Construction Company in the amount of $11,668,160 for drainage improvements in the Cimarron Subdivision Sections 2, 3, 4 and 5 for Precinct 4, and for the County Clerk to execute any applicable bonds to be received (220201), MWDBE Contracted Goal: 19%.
end
Background and Discussion:
The Cimarron Secs 2, 3, 4, and 5 Subdivision Drainage Improvements Project is located west of Harris County in the Barker Reservoir. The Cimarron Subdivision consist of concrete curb and gutter with inlets and storm sewer drainage system which out falls into HCFCD T101-07-00. After further evaluation of the planning phase study report, the project proposed improvements and scope is to upsize the storm sewer system and adding additional inlets to provide better conveyance and drainage capacity. Construction of these improvements to be performed by R Construction Civil, LLC, ensures that that the project is built in accordance with Harris County and Harris County Flood Control regulations.
Expected Impact:
This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This award is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the Cimarron subdivision homeowners, Harris Co...