File #: 22-4565    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/22/2022 In control: Commissioners Court
On agenda: 8/2/2022 Final action: 8/2/2022
Title: Request for approval of a change in contract with Aranda Brothers Construction Co., Inc. in connection with Crosby Lynchburg Road Phase 4, adding 48 calendar days, with an addition in the amount of $32,121.50, Job No. 21/0008-3, UPIN 18102MF0S701, Precincts 2 & 3, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County's M/WBE Program).

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 21/0008

Vendor/Entity Legal Name (if applicable): Aranda Brothers Construction Co., Inc.

 

MWDBE Contracted Goal (if applicable): 0%

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Aranda Brothers Construction Co., Inc. in connection with Crosby Lynchburg Road Phase 4, adding 48 calendar days, with an addition in the amount of $32,121.50, Job No. 21/0008-3, UPIN 18102MF0S701, Precincts 2 & 3, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County’s M/WBE Program).

end

 

Background and Discussion:

 

Project includes reconstruction of the existing Crosby Lynchburg Road from the existing asphalt road to a concrete five-lane roadway with curb and gutter.  Change includes a pay item for the TCEQ permit, low profile barriers, flowable fill, and a special drill shaft bit required due to existing soil conditions.  Change also includes time for utility conflict delays, completing the additional work and for plan revisions required to complete the project.

 

Expected Impact:

 

Changes allow the project to be completed in accordance with the original intent of the project and to allow the Contractor time to complete this additional work without penalty.

 

Alternative Options:

 

Reduce the scope of work to eliminate the need for the additional items of work.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

02/26/2021

269

Contract Award

10/26/2021

51

Contract Amendment for additional funds and extension of project term

02/02/2022

52

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable): Crosby Lynchburg Road.

Precinct(s): Precincts 2 & 3

 

Fiscal and Personnel Summary

Service Name

Reconstruction

 

SFY 22

FY 23

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$32,121.50

$

$

Total Incremental Expenditures

$32,121.50

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Other

$32,121.50

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$32,121.50

$

$

Additional Budget Requested

Choose an item.

 

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$32,121.50

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: August 02, 2022

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Julia Bond, P.E., Manager HCED-CPD

Attachments (if applicable): County Auditor’s Form 1258B