File #: 22-4558    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/22/2022 In control: Commissioners Court
On agenda: 8/2/2022 Final action: 8/2/2022
Title: Request for approval of a change in contract with WadeCon, LLC in connection with Intersection Improvements - Barker Cypress Road at Queenston Boulevard - 2019, adding 65 calendar days, with an addition in the amount of $22,127.00, Job No. 20/0259-1, UPIN 191033954023, Precinct 3, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County's M/WBE Program).
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 20/0259
Vendor/Entity Legal Name (if applicable): WadeCon, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with WadeCon, LLC in connection with Intersection Improvements - Barker Cypress Road at Queenston Boulevard - 2019, adding 65 calendar days, with an addition in the amount of $22,127.00, Job No. 20/0259-1, UPIN 191033954023, Precinct 3, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County's M/WBE Program).
end

Background and Discussion:

Project includes reconstruction of the intersection of Barker Cypress Road at Queenston Boulevard. Change includes fog seal to provide an even finish to the completed pavement and ground box relocations. Change also includes a time extension for the following: ground box relocations (15 days), fog seal (30 days), SET changes (15 days) and hard freeze (5 days).

Expected Impact:

Changes allow additional work needed to complete the project within the original scope and in accordance with Precinct requirements. Additional time allows the Contractor to complete additional work without penalty.

Alternative Options:

Reduce the scope of the project to eliminate the need for additional work.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
11/10/2020
21.d.8.p
Contract Award

Location:
Address (if applicable): Barker Cypress Road at Queenston Bou...

Click here for full text