Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): 23103MF2QZ01
Vendor/Entity Legal Name (if applicable): Scientech Engineers, Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to negotiate with Scientech Engineers, Inc. for Professional Engineering Services in connection with South Diamondhead Blvd - from 500-ft west of Sea Palms Dr to west of Boom Dr - 2022, Precinct 3.
end
Background and Discussion:
Addition of remaining two eastbound lanes of a four-lane boulevard with asphalt pavement from South Diamondhead Blvd - from 500-ft West of Sea Palms Dr to West of Boom Dr. Repair the two existing westbound lanes and construct two westbound lanes of the bridge over Gum Gully.
Expected Impact:
The roadway expansion will improve the traffic operations of the area.
Alternative Options:
An alternative option is to not expand South Diamondhead Blvd.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any): N/A
Date |
Agenda Item # |
Action Taken |
|
|
|
Location:
Address (if applicable): South Diamondhead Blvd
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
|
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$ |
$ |
$ |
Total Incremental Expenditures |
$ |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: August 2, 2022
Anticipated Implementation Date (if different from Court date): August 23, 2022
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Ashleigh Williams, Project Manager, HCED