Harris County Logo
File #: 22-4490    Version: 1 Name:
Type: Contract - Award Status: Agenda Ready
File created: 7/21/2022 In control: Commissioners Court
On agenda: 8/2/2022 Final action: 8/2/2022
Title: Request for approval of a development agreement with Glomic Properties, LLC, to establish permit coverage costs for dedication of needed environmental enhancements. (Little Cypress Creek Watershed, Project ID L100-00-00-Y007, Agreement No. 2022-154, Precinct 4). Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Attachments: 1. 080222 AGMT GLOMIC 2022-154 PCT 4 backup

Department: Flood Control District

Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): L100-00-00-Y007

Vendor/Entity Legal Name (if applicable): Glomic Properties, LLC

 

MWDBE Contracted Goal (if applicable):

MWDBE Current Participation (if applicable):

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a development agreement with Glomic Properties, LLC, to establish permit coverage costs for dedication of needed environmental enhancements. (Little Cypress Creek Watershed, Project ID L100-00-00-Y007, Agreement No. 2022-154, Precinct 4). Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program.

end

 

Background and Discussion:

The agreement represents the Developers voluntary joining of the Little Cypress Creek Regional Stormwater Quality Program, established to meet needs of the Little Cypress Creek Regional Frontier Program. The stormwater quality program represents three of the goals listed in the interim guidelines for new development in Little Cypress Creek; provide for regional stormwater quality features, facilitate multi-use objectives, and facilitate long term maintenance objectives. Glomic Properties, LLC during development sought to complete improvements identified in the Little Cypress Creek Interim guidelines, detention excavation equal to HCFCD environmental enhancement costs, and offset water quality required by the development area to meet Harris County Stormwater Quality Regulations. The agreement would signify the acceptance of the identified drainage area for coverage under the HCFD Regional Little Cypress Creek Stormwater Quality Permit for in-kind excavation work.

 

Expected Impact:

Increase effective detention volume at (L114-01-00) conveyance channel and offset the Flood Control District burden of wetland plantings cost through in-kind water quality excavation. Glomic Properties, LLC will claim limited water quality volume from the Stormwater Quality Program ledger and allocate to the L514-01-00 basin.   Increases of impervious surface beyond the development threshold will require developers to provide additional water quality improvements. 

 

 

Alternative Options:

Without approval of this agreement, Glomic Properties would need to retrofit ROW to install disjointed water quality treatment features and be required to obtain individual permits. This can lead to disjointed water quality maintenance for the community, limit water quality improvements to hard scape options that generally target floatables and not pollutants of concern, such as bacteria. This will increase the cost burden on HCFCD to conduct additional excavation for water quality improvements and wetland planting costs.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

02/11/2014

1.d.5

Interim Guidelines for New Development

 

Location: N/A

Address (if applicable):

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

4.a.5 - Planning Services

 

SFY 22

FY 23

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: August 2, 2022

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Tina Petersen, Ph.D., P.E., Executive Director, Flood Control District

Attachments (if applicable): Agreement and Map