File #: 22-4638    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 7/26/2022 In control: Commissioners Court
On agenda: 8/2/2022 Final action: 8/2/2022
Title: Request for approval to execute a service outlet location statement for the installation of an electric meter with CenterPoint Energy and authorize the County Auditor to pay monthly bills for 3155 1/2 Atascocita Rd, Humble, TX 77396 (intersection of Atascocita Rd at Blackstone Trails Dr) for electrical power serving a traffic signal, Precinct 3.
Attachments: 1. 22-4638 SOLS - 3155.5 Atascocita Rd at Blackstone Trails Dr P3.pdf

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

 

Project ID (if applicable): UPIN 22035MF2GC01

Vendor/Entity Legal Name (if applicable): CenterPoint Energy

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to execute a service outlet location statement for the installation of an electric meter with CenterPoint Energy and authorize the County Auditor to pay monthly bills for 3155 ½ Atascocita Rd, Humble, TX 77396 (intersection of Atascocita Rd at Blackstone Trails Dr) for electrical power serving a traffic signal, Precinct 3.

end

 

Background and Discussion:

Traffic Signal - Atascocita Rd at Blackstone Trails Dr. is a project to enhance traffic movements at the existing intersection. The service outlet location statement is needed to establish electrical service from CenterPoint Energy to power the traffic signal.

 

Expected Impact:

Approval of the service outlet location statement will allow CenterPoint Energy to provide electrical service to the traffic signal, which is needed to enhance the public safety and operation of the intersection of Atascocita Rd at Blackstone Trails Dr.

 

Alternative Options:

All Traffic Signals require a power source, which is typically obtained through CenterPoint Energy. Alternative options are to place a generator, which is not reliable, or not install the traffic signal at the intersection. Both options pose a public safety concern and will impact the operation and increase delay of the intersection.  

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): 3155 ½ Atascocita Rd, Humble, TX 77396

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

 

 

SFY 22

FY 23

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$2,100.00

$700.00

$3,600.00

Total Incremental Expenditures

$2,100.00

$700.00

$3,600.00

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

1000 - General Fund

$2,100.00

$700.00

$3,600.00

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$2,100.00

$700.00

$3,600.00

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$2,100.00

$700.00

$3,600.00

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: August 2, 2022

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Tina Liu, P.E. Interim Manager, Traffic Design and Operations                     

Attachments (if applicable): SOLS