Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 220064
Vendor/Entity Legal Name (if applicable): J Rivas Construction, LLC
MWDBE Contracted Goal (if applicable): 15%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to J Rivas Construction, LLC in the amount of $2,602,960 based on estimated quantities and fixed unit pricing for new construction and maintenance of sidewalks and related items for the Office of the County Engineer for a one (1) year initial term, with four (4) one-year renewal options, and for the County Clerk to execute any applicable bonds to be received for the budgeted amount (220064), MWDBE Contracted Goal: 15%.
end
Background and Discussion:
Harris County requested contract documents for sidewalk and related items term contract.
Expected Impact:
Harris County will have access to services pertaining to sidewalk and related items term contract.
Alternative Options:
Harris County would be required to determine other resources for sidewalk and related items term contract.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
X Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
N/A |
N/A |
N/A |
Location:
Address (if applicable):
Precinct(s): Countywide
Fiscal and Personnel Summary |
Service Name |
|
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$800k |
$ |
$ |
Non-Labor Expenditures |
$ |
$ |
$ |
Total Incremental Expenditures |
$800k |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
1070 - Mobility Fund |
$800k |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$800k |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: July 19, 2022 Commissioner’s Court
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Gregory Van Russ, Jr., Assistant Project Manager, HCED-TS, Kenneth Jackson, Senior Buyer, HC Purchasing
Attachments (if applicable): Award Recommendation Documents