File #: 22-4512    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/21/2022 In control: Commissioners Court
On agenda: 8/2/2022 Final action: 8/2/2022
Title: Request for approval of a fifth contract amendment with HCHA Redevelopment Authority, Inc., to ratify Amendment Four, adjust certain budget items, and increase the total amount of funding of The Hollows project by $272,528 utilizing CDBG-DR FY2017 funds.
Attachments: 1. The Hollows- Fifth Amendment 8.2.22
Department: Community Services
Department Head/Elected Official: Adrienne M. Holloway, Ph.D., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): D2017-062
Vendor/Entity Legal Name (if applicable): HCHA Redevelopment Authority, Inc.

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval of a fifth contract amendment with HCHA Redevelopment Authority, Inc., to ratify Amendment Four, adjust certain budget items, and increase the total amount of funding of The Hollows project by $272,528 utilizing CDBG-DR FY2017 funds.
end

Background and Discussion:
On April 7, 2020, Commissioners Court approved an agreement between the Harris County and HCHA Redevelopment Authority, Inc. for The Hollows Project. On October 13, 2020; August 10, 2021; January 4, 2022; and April 5, 2022; Commissioners Court approved the First, Second, Third, and Fourth Amendments that amended the agreement, respectively. Attached for Commissioners Court review and approval is the fifth amendment to the agreement between Harris County and HCHA Redevelopment Authority, Inc., for the above-described project to increase the CSD Management and Oversight and HCED Inspections line-item to $523,810. This change in the budget results in an increase to the total CDBG-DR FY17 funds by $272,528.00 and the total amount of funding for this project to $39,098,647.00.

Expected Impact:
The expected impact is to adjust the budget to allow for the project to be completed. The fiscal impact of the amendment to the County is $272,528 in CDBG-DR FY17 funds.

Alternative Options:
If not approved, the project the budget would not match the needs of the project.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
X Housing
_ Public Health
_ ...