Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable):
Vendor/Entity Legal Name (if applicable):
MWDBE Participation (if applicable):
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of best proposal meeting requirements to CFI Mechanical, Inc. in the amount of $1,371,182 for air conditioning replacement in the computer room at Annex 18 for Facilities & Property Maintenance, subject to applicable bonds to be received (210167).
end
Background and Discussion:
Computer Room A/C units on the 3rd floor of Annex 18 are dependent on a chilled water source for proper operations. If the building’s chilled water system was to go offline, the Computer Room A/C units would shutdown. The servers in the computer room would over heat and shutdown. The servers on the 3rd floor are the main servers for Harris County. To increase Computer Room A/C units reliability, a second cooling source is needed. The new Computer Room A/C units will be equipped with Freon cooling units as backup. The Freon cooling units will be located on the roof of the facility.
Expected Impact:
The Computer Room A/C units will no longer be dependent a chilled water system to provide cooling the important computer servers located on the 3rd floor.
Alternative Options:
No alternates.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
6/7/2021 |
21-2526 |
Advertise project to bid. |
Location:
Address (if applicable):Annex 18, 406 Caroline St, Houston TX 77002
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
- |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
800,000 |
- |
- |
Non-Labor Expenditures |
935,000 |
- |
- |
Total Incremental Expenditures |
1,735,000 |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
- |
- |
- |
Additional Budget Requested |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
- |
- |
- |
Total Funding Sources |
- |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: 12/2021
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Jeff Parker, CIP Special Project Manager, Engineering/FPM
Attachments (if applicable):