Department: Flood Control District
Department Head/Elected Official: Alan R. Black, P.E., Interim Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): M124-00-00-E001
Vendor/Entity Legal Name (if applicable): R. Miranda Trucking and Construction, LLC
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 2 with R. Miranda Trucking and Construction, LLC, for the channel excavation from SH 249 to FM 2920 and stormwater detention basin phase I, adding 22 calendar days and resulting in no change to the contract amount. (Willow Creek Watershed, Project ID M124-00-00-E001, Job No. 20/0270, Precinct 4).
end
Background and Discussion:
The installation of a new live gas line under a privately owned road required an extension of the temporary bypass be added to work scope and took six days to complete. The contractor has experienced 16 days of inclement weather that has impacted the contractor's critical path. The modified work scope results in a net increase of $0 to the contract and 22 days added to the contract duration.
Expected Impact:
This RCA is required to complete the District construction contract under original or needed revised scope. Timely execution is appreciated in order to mitigate any potential delays from the contractor.
Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
11/10/2020 |
21.d.8.k |
Contract Award |
10/12/2021 |
117. |
Change in Contract No. 1 |
Location: From SH 249 to FM 2920
Address (if applicable):
Precinct(s): Precinct 4
Fiscal and Personnel Summary |
Service Name |
4.a.2. - Construction Services |
|
FY 21-22 |
FY 22 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$ |
$ |
$ |
Total Incremental Expenditures |
$ |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: November 30, 2021
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Alan R. Black, P.E., Interim Executive Director
Matthew K. Zeve, P.E., Deputy Executive Director
Attachments (if applicable): Change in Contract and Map