Department: Flood Control District
Department Head/Elected Official: Alan R. Black, P.E., Interim Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): B104-03-02.1-X008
Vendor/Entity Legal Name (if applicable): Magellan Pipeline Company, L.P.
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval of an agreement with Magellan Pipeline Company, L.P., in the amount of $39,430, for a project which includes crossing the pipeline with construction equipment and removal and replacement of concrete channel side slopes in the vicinity of the pipeline. (Armand Bayou Watershed, Project ID B104-03-02.1-X008, Agreement No. 2022-52, Precinct 2).
end
Background and Discussion:
The District requires an agreement by and between the District and Magellan Pipeline Company, L.P., allowing the District to cross the pipeline with construction equipment. Also, to remove and replace the concrete side slope through which the pipeline presently penetrates through as an aerial crossing over the channel.
Expected Impact:
The project will repair and stabilize the channel side slopes preventing further failure of the concrete side slopes in the vicinity of the Magellan pipeline. If an agreement is not obtained, repair of the concrete channel side slopes will not occur and the degrading soil behind the concrete side slopes will continue to fail resulting in the complete collapse of the channel side slopes.
Alternative Options:
Do not proceed with obtaining an agreement and repair of the channel. The channel will continue to deteriorate causing more impacts to the channel and surrounding property.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any): N/A
Date |
Agenda Item # |
Action Taken |
|
|
|
Location: Intersection of B104-03-02.1 Channel and Galveston Road (west of El Dorado Boulevard)
Address (if applicable):
Precinct(s): Choose an item.
Fiscal and Personnel Summary |
Service Name |
4.a.3 - Engineering Services |
|
FY 21-22 |
FY 22 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$39,430 |
$ |
$ |
Total Incremental Expenditures |
$39,430 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Tax Revenue - FCD |
$39,430 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$39,430 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$39,430 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: November 30, 2021
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Alan R. Black, P.E., Interim Executive Director
Matthew K. Zeve, P.E., Deputy Executive Director
Attachments (if applicable): Agreement and Map