Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 21/0302
Vendor/Entity Legal Name (if applicable):
MWDBE Participation (if applicable):
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of only bid to GLM Contracting, Inc. in the amount of $204,287 based on estimated quantities and fixed unit pricing for concrete pavement repair and related items in Precinct 1, subject to applicable bonds to be received for the budgeted amount (210302).
end
Background and Discussion:
Precinct 1 requested the preparation of an on-call term contract for concrete pavement repairs and related items.
Expected Impact:
Precinct 1 will have access to services pertaining to concrete pavement repairs and related items.
Alternative Options:
Precinct 1 would be required to determine other resources for concrete pavement repairs and related items.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
x Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
N/A |
N/A |
N/A |
Location:
Address (if applicable):
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
- |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
- |
- |
- |
Non-Labor Expenditures |
$600,000.00 |
- |
- |
Total Incremental Expenditures |
$600,000.00 |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
- |
- |
- |
Additional Budget Requested |
PCT 1 - |
$600,000.00 |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
- |
- |
- |
Total Funding Sources |
$600,000.00 |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: November 30, 2021 Court Date
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: John Hubbard, P.E. Project Manager, HCED
Attachments (if applicable): Award Documents