Title: Request for approval of a Preliminary Investment Memo for the Coons Road Water-Sewer Connection Construction project for $331,200 and initial commercial paper funding of $335,000, Precinct 4.
Attachments: 1. 21-6211 PIM - Coons Rd Water-Sewer.pdf
Department: County Engineer
Department Head: Loyd Smith, P.E. Interim County Engineer

Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Preliminary Investment Memo
Project Name: Coons Rd Water-Sewer Connection Construction
Project ID (if applicable):
Vendor Legal Name (if applicable):
MWDBE Participation (if applicable):

Managing Entity: County Engineer
Incremental Expenditures Requested: $331,200
Total Estimated Project Cost: $547,200


Request Summary:
title
Request for approval of a Preliminary Investment Memo for the Coons Road Water-Sewer Connection Construction project for $331,200 and initial commercial paper funding of $335,000, Precinct 4.
end

Project Description:
The proposed project is to extend MUD368's water and sewer lines along Coons Road, from the current MUD368 water and sewer line termination located just north of Timbertech Lane to the east border of the property at 23828 Tomball Parkway.
The estimated time to complete the MUD district portion of the work is estimated to be 12 months.
Project Scope:
First the MUD district will need to extend the water and sewer lines from their current point of termination north of Timbertech land on Coons Road to the eastern border of the Harris County site. This involves:
* Extend a 12-inch water line approximately 700 feet
* Extend an 8-inch sanitary sewer line approximately 700 feet
Both lines will cross under Timbertech Lane, a paved road, and continue along the west side of Coons Road.
After the MUD district has completed their portion of the work with the meters in place, Harris County will connect from the meter to the building. We are currently estimating 600 linear feet of 3-inch water line and 4-inch sanitary sewer line, though final sizes and lengths will be determined in design.
This project will be split into two phases:
1. Phase 1:
a. Construction of the MUD water and sewer line along Coons Road from Timbertech Lane to the eastern boundary o...