Department: County Engineer
Department Head/Elected Official: Loyd Smith, P.E, Interim County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): 17102MF0PM01
Vendor/Entity Legal Name (if applicable): City of Houston
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval to execute First Amendment to an Interlocal agreement with City of Houston for the County to construct Phase 2 improvements to El Dorado Boulevard from Clear Lake City Boulevard to approximately 585-feet north of Willow Shores Drive, UPIN 17102MF0PM01, Precinct 2.
end
Background and Discussion:
Original ILA was previously approved by CC on April 10, 2018 for construction of Phase 1 improvements to El Dorado Boulevard from Clear Lake City Boulevard to approximately 585-feet north of Willow Shores Drive, UPIN 17102MF0PM01, Precinct 2
The project phase 1 is to construct two southbound lanes, to complete the existing two-lane concrete section to a four-lane concrete boulevard within existing ROW limits. The project also modifies the existing traffic signal systems at Brook Forest Drive and at Clear Lake City Boulevard. The new lanes will cross the bayou with a new bridge structure. Phase 2 of the project is to install storm drainage to address Atlas 14. This is a joint project between Harris County and the City of Houston.
The amendment is for additional funding for Phase 2 to construct additional drainage to accommodate Atlas 14 requirements.
Expected Impact:
Atlas 14 drainage improvements, shared use path, community connectivity.
Alternative Options:
Provide other detention options that would require additional community engagement.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
4/10/18 |
l.1.h.3 |
Interlocal Agreement |
Location:
Address (if applicable): El Dorado Boulevard from Clear Lake City Boulevard to approximately 585-feet north of Willow Shores
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
Construction |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
- |
- |
- |
Non-Labor Expenditures |
- |
- |
- |
Total Incremental Expenditures |
- |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
Pct 2 Mobility |
$3,146,000 |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
- |
- |
- |
Additional Budget Requested |
Pct 2 Mobility- |
$1,308,381.80 |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
$1,308,381.80 |
- |
- |
Total Funding Sources |
$4,454,381.80 |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: October 12, 2021
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Tom Vu, P.E., Project Manager, HCED
Attachments (if applicable): First Amendment to ILA with COH