Harris County Logo
File #: 21-5443    Version: 1 Name:
Type: Contract - Award Status: Agenda Ready
File created: 10/5/2021 In control: Commissioners Court
On agenda: 10/12/2021 Final action: 10/12/2021
Title: Request for approval of an award on the basis of only bid to D&W Contractors, Inc. in the amount of $16,742,464 for storm sewer installation and maintenance in Precinct 2, subject to applicable bonds to be received (210223).
Attachments: 1. 21-5443 Award Job No. 210223 D&W Contractors, Inc..pdf
Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable):
Vendor/Entity Legal Name (if applicable):
MWDBE Participation (if applicable): N/A

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of only bid to D&W Contractors, Inc. in the amount of $16,742,464 for storm sewer installation and maintenance in Precinct 2, subject to applicable bonds to be received (210223).
end


Background and Discussion:

Construction of storm sewer, structures and detention ponds in the Harris County Precinct 2 limits.

Expected Impact:

Construction of storm sewer, structures and detention ponds will improve flooding conditions and
enhance drainage capacity, thereby improving mobility and safety for all road users and flood resiliency
for all adjacent properties. This purchase order will ensure that all construction materials used in the
project are of acceptable quality as required by state law.

Alternative Options:

Without professional architectural and engineering services to perform the study and design the construction of residential developments the General Land Office will not approve funding for this project and could potentially end all the project.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
Housing
_ Public Health
_ Transportation
X_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):


Location:
Address (if applicable):
Precinct(s): Precinct 2


Fiscal and Personnel Summary
Service Name
-
FY 21-22
Estimates



FY 22
Next 3 FYs
Incremental Expenditures
Labor Expenditures
-
-
-
Non-Labor Expenditures
-
-
-
Total Incremental Expenditures
-
-
-
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify)
Existing
Budget
Fund 2601- 2017 Hurricane Harvey Community Development Block Grant - Disaster Recovery Funds -
$1...