Request for approval of a study report prepared by IDCUS INC for Clay Road 3-4500' West of Porter Road to West of Porter Road, Precinct 3.
end
Background and Discussion:
ATN and PSA were previously submitted to court to negotiate with and to start working with IDCUS,Inc. on the study for Clay Road 3-4500' West of Porter Road to West Porter Road, Precinct 3.
Expected Impact:
The project will address current and future traffic volumes, reduce delays, provide connectivity to schools and neighborhood destinations, improve safety for pedestrians and motorists, improve roadway conditions, and reduce potential of structural flooding with drainage improvements.
Alternative Options: N/A
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
2/27/2018
Contract Award
1/29/2019
1st Contract Amendment for additional funds
8/27/2019
2nd Contract Amendment for additional funds
4/28/2020
3rd Contract Amendment for additional funds
10/27/2020
4th Contract Amendment for additional funds
6/29/2021
5th Contract Amendment for additional funds
Location:
Address (if applicable): ): Clay Road 3-4500' West of Porter Road to West Porter Road, Precinct
Precinct(s): Precinct 3
Fiscal and Personnel Summary
Service Name
-
FY 21-22
Estimates
FY 22
Next 3 FYs
Incremental Expenditures
Labor Expenditures
-
-
-
Non-Labor Expenditures
-
-
-
Total Incremental Expenditures
-
-
-
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other...
Click here for full text