File #: 21-5410    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/4/2021 In control: Commissioners Court
On agenda: 10/12/2021 Final action: 10/12/2021
Title: Request for approval of Change in Contract No. 16 with Lecon, Inc., for general drainage system repairs - south, adding 210 calendar days with no change to the contract amount. (Project ID Z100-00-00-X281, Job No. 19/0175, Countywide).
Attachments: 1. 21-5410 CIC LECON Z100-X281 CW backup

Department: Flood Control District

Department Head/Elected Official: Alan R. Black, P.E., Interim Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Z100-00-00-X281

Vendor/Entity Legal Name (if applicable): Lecon, Inc.

MWDBE Participation (if applicable): N/A

 

Request Summary (Agenda Caption):

title

Request for approval of Change in Contract No. 16 with Lecon, Inc., for general drainage system repairs - south, adding 210 calendar days with no change to the contract amount. (Project ID Z100-00-00-X281, Job No. 19/0175, Countywide).

end

 

Background and Discussion:

The original contract duration was 730 days (two years). This month, we are reaching the end of the

original contract duration but have significant balance remaining on the contract. This contract change

extends the contract duration by 210 days to add two additional sites E101-00-00-X030 and W167-04-00-

X005 utilizing existing contract funds. This change reallocates quantities between existing pay items to

reflect actual measured quantities and projected quantities for the added sites. The major quantity

extensions include riprap, granular fill, channel lining removal, and backslope swale grading.

 

Expected Impact:

This RCA is required in order to complete the District construction contract under original or needed

revised scope. Timely execution is appreciated in order to mitigate any potential delays from the

contractor.

 

Alternative Options:

This is an active construction contract, so there are not many alternatives to approving a change order

other than cancelling the contract which is not recommended as doing so would substantially delay the

remaining work in the construction contract.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

06/04/2019

21.c.1.e

Request to Advertise

07/30/2019

21.d.10.j

Contract Award

12/17/2019

2.c.3

Contract Amendment

04/28/2020

2.c.2

Contract Amendment

07/28/2020

2.c.6

Contract Amendment

10/13/2020

2.b.1

Contract Amendment

11/10/2020

2.c.2

Contract Amendment

08/24/2021

117.

Contract Amendment

 

Location:

Address (if applicable): N/A

Precinct(s): Countywide

 

 

Fiscal and Personnel Summary

Service Name

N/A

FY 21-22

Estimates

 

 

 

FY 22

Next 3 FYs

Incremental Expenditures

Labor Expenditures

-

-

-

Non-Labor Expenditures

-

-

-

Total Incremental Expenditures

-

-

-

Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify)

Existing Budget

-

-

-

-

 

-

-

-

-

 

-

-

-

-

Total Current Budget

-

-

-

Additional Budget Requested

-

-

-

-

 

-

-

-

-

 

-

-

-

-

Total Additional Budget Requested

-

-

-

Total Funding Sources

-

-

-

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

 

Anticipated Implementation Date: October 12, 2021

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Alan R. Black, P.E., Interim Executive Director

Matthew K. Zeve, P.E., Deputy Executive Director

 

Attachments (if applicable): Change in Contract