File #: 21-5409    Version: 1 Name:
Type: Negotiation Status: Passed
File created: 10/4/2021 In control: Commissioners Court
On agenda: 10/12/2021 Final action: 10/12/2021
Title: Request for approval of Change in Contract No. 2 with L.N. McKean, Inc., for phase 4 channel conveyance improvements, adding 31 calendar days and resulting in an addition of $1,680 to the contract amount. (Sims Bayou Watershed, Project ID C106-03-00-C007, Job No. 19/0364, Precinct 2).
Attachments: 1. 21-5409 CIC LN MCKEAN PCT 2 backup
Department: Flood Control District
Department Head/Elected Official: Alan R. Black, P.E., Interim Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): C106-03-00-C007
Vendor/Entity Legal Name (if applicable): L.N. McKean, Inc.
MWDBE Participation (if applicable): N/A

Request Summary (Agenda Caption):
title
Request for approval of Change in Contract No. 2 with L.N. McKean, Inc., for phase 4 channel conveyance improvements, adding 31 calendar days and resulting in an addition of $1,680 to the contract amount. (Sims Bayou Watershed, Project ID C106-03-00-C007, Job No. 19/0364, Precinct 2).
end

Background and Discussion:
The purpose of this change is to extend the contract time due to added scope and inclement weather
experienced by the contractor as per the provisions in the contract. The change also adjusts pay item
quantities for a storm sewer outfall where the actual size further upstream of our work was found to be
larger necessitating us to upsize the planned outfall from 24" reinforced concrete pipe (RCP) to 36" RCP.

Expected Impact:
This RCA is required in order to complete the construction contract under original or needed revised scope. Timely execution is appreciated in order to mitigate any potential delays from the Contractor. Changes in contract result from categories identified in the District document management system.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order
other than cancelling the contract which is not recommended as doing so would substantially delay the
remaining work in the construction contract.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
12/03/2019
22.c.1.a
Request to Advertise
01/07/202...