Harris County Logo
File #: 21-5407    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/4/2021 In control: Commissioners Court
On agenda: 10/12/2021 Final action: 10/12/2021
Title: Request for approval of Change in Contract No. 18 with Lecon, Inc., for general drainage system repairs - north, resulting in an addition of $666,411 to the contract amount. (Project ID Z100-00-00-X280, Job No. 19/0166, Countywide).
Attachments: 1. 21-5407 CIC LECON Z100-X280 CW backup

Department: Flood Control District

Department Head/Elected Official: Alan R. Black, P.E., Interim Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Z100-00-00-X280

Vendor/Entity Legal Name (if applicable): Lecon, Inc.

MWDBE Participation (if applicable): N/A

 

Request Summary (Agenda Caption):

title

Request for approval of Change in Contract No. 18 with Lecon, Inc., for general drainage system repairs - north, resulting in an addition of $666,411 to the contract amount. (Project ID Z100-00-00-X280, Job No. 19/0166, Countywide).

end

 

Background and Discussion:

The purpose of this modification in contract is to adjust planned and projected quantities necessary for the following: added scope of work to P121-00-00-X009 from request for information 81, addition of G103-33-00-X008, G103-80-03.1-X032, and K100-00-00-X097 to the contract, minor corrections to various pay items based off of completed and anticipated work. This work was directed and authorized by the District Design Project Manager.

 

Expected Impact:

This RCA is required in order to complete the District construction contract under original or needed

revised scope. Timely execution is appreciated in order to mitigate any potential delays from the

contractor.

 

Alternative Options:

This is an active construction contract, so there are not many alternatives to approving a change order

other than cancelling the contract which is not recommended as doing so would substantially delay the

remaining work in the construction contract.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

07/09/2019

18.d.7.e

Contract Award

11/12/2019

2.c.1

Contract Amendment

11/10/2020

2.c.1

Contract Amendment

12/15/2020

2.c.1

Contract Amendment

04/27/2020

97.

Contract Amendment

07/20/2021

147.

Contract Amendment

 

Location:

Address (if applicable): N/A

Precinct(s): Countywide

 

 

Fiscal and Personnel Summary

Service Name

4.a.2 - Construction Services

FY 21-22

Estimates

 

 

 

FY 22

Next 3 FYs

Incremental Expenditures

Labor Expenditures

-

-

-

Non-Labor Expenditures

667K

-

-

Total Incremental Expenditures

667K

-

-

Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify)

Existing Budget

HCFCD O&M

15.8M

-

-

 

-

-

-

-

 

-

-

-

-

Total Current Budget

15.8M

-

-

Additional Budget Requested

HCFCD O&M

667K

-

-

 

-

-

-

-

 

-

-

-

-

Total Additional Budget Requested

667K

-

-

Total Funding Sources

16.4M

-

-

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

 

Anticipated Implementation Date: October 12, 2021

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Alan R. Black, P.E., Interim Executive Director

Matthew K. Zeve, P.E., Deputy Executive Director

 

Attachments (if applicable): Change in Contract