Department: County Engineer
Department Head/Elected Official: Loyd Smith, P.E., Interim County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 21102MF23N01
Vendor/Entity Legal Name (if applicable): AKV Consultants LLC
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval to execute an amendment to an agreement with AKV Consultants LLC in the amount of $7,796.70 for Professional Engineering Services to provide improvements to a sidewalk along Normandy Street from Woodforest Blvd. to Wallisville Rd., UPIN 21102MF23N01, Precinct 2.
end
Background and Discussion:
ATN and PSA was previously submitted to court to negotiate with and to start working with AKV CONSULTANTS LLC on the design for the Sidewalk - Normandy Street from Woodforest Blvd. to Wallisville Rd. - 2021 project. Additional fee ($7,796.70) needed to complete metes and bounds for 10 parcels as a result of UVEs.
Expected Impact:
Sidewalk Construction
Alternative Options: N/A
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
3/9/2021 |
|
ATN |
5/11/2021 |
|
Professional Services Agreement |
Location:
Address (if applicable): Sidewalk - Normandy Street from Woodforest Blvd. to Wallisville Rd. - 2021
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
Design Services |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
- |
- |
- |
Non-Labor Expenditures |
$205,146.49 |
- |
- |
Total Incremental Expenditures |
$205,146.49 |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
- |
$197,349.79 |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
$197,349.79 |
- |
- |
Additional Budget Requested |
- |
$7,796.70 |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
$7,796.70 |
- |
- |
Total Funding Sources |
$205,146.49 |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: October 12, 2021
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Loretta Lau, P.E., Project Manager, HCED Phone: 713.274.3675
Email: Loretta.Lau@eng.hctx.net <mailto:Loretta.Lau@eng.hctx.net>
Attachments (if applicable): Contract Document Addendum