Department: County Engineer
Department Head/Elected Official: Loyd Smith, P.E., Interim County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Policy
Project ID (if applicable): 21102MF24101
Vendor/Entity Legal Name (if applicable): Lockwood Andrews & Newnam, Inc.
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval of a study report prepared by Lockwood Andrews & Newnam, Inc. for Quiet Zones at Various Locations, Precinct 2.
end
Background and Discussion:
The goal of this study report is to evaluate six UPRR and BNSF railroad crossings between IH-45 and Hardy Toll Road for potential quiet zones by identifying safety and noise issues, developing potential solutions and an engineering estimate of probable cost, which will provide a firm foundation of information to seek funding partners from regional stakeholders and agencies.
Expected Impact:
The outcome of the study is to provide adequate information and direction that will aid in seeking funding partners from regional stakeholders and agencies
Alternative Options: N/A
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any): N/A
Date |
Agenda Item # |
Action Taken |
|
|
|
Location: Fulton Street, Donlen Street, Helmers Street, Irvington Boulevard, W. Hardy Street (2)
Address (if applicable):
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
- |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
- |
- |
- |
Non-Labor Expenditures |
- |
- |
- |
Total Incremental Expenditures |
- |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
- |
- |
- |
Additional Budget Requested |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
- |
- |
- |
Total Funding Sources |
- |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: October 12, 2021
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Joy Ogunnubi, Project Manager, HCED
Attachments (if applicable): 2021-07-08 Quiet Zones Study Report - Final