Department: County Engineer
Department Head/Elected Official: John R. Blount, P.E., County Engineer
Regular or Supplemental RCA:
☒ Regular RCA
☐ Supplemental RCA
Type of Request: Authorization to Negotiate
Project ID (if applicable): UPIN 19103MF15U01
Vendor/Entity Legal Name (if applicable): Lockwood, Andrews, & Newnam, Inc (LAN)
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval to negotiate with Lockwood, Andrews & Newnam, Inc. for Professional Engineering Services in connection with Coles Crossing Subdivision Drainage Improvements as part of the Flood Control District Bond Program, UPIN 19103MF15U01, Precinct 3.
end
Background and Discussion:
This project is located in northwest Harris County in the Cypress Creek watershed. Coles Crossing consists of a curb and gutter storm sewer drainage system that drains to either Dry Creek on the west side or to interior channels on the east side of the subdivision. The scope and proposed improvements that were recommended during the planning study of this project will be reevaluated based on current data and data received from the Coles Crossing community. Improvements will comply with Harris County standards.
Expected Impact:
In implementing the proposed drainage improvements, this project seeks to reduce structural flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to the homes in the community. This will reduce the financial, physical, and emotional burden flood damage placed on homeowners and will reduce the financial impact costs to the homeowners, Harris County, and FEMA.
Alternative Options:
N/A
Alignment with Goal(s):
☐ Justice and Safety
☐ Economic Opportunity
☐ Housing
☐ Public Health
☐ Transportation
☒ Flooding
☐ Environment
☐ Governance and Customer ServicePrior Court Action (if any): N/A
Location:
Address (if applicable list below):
☐ Countywide
☐ Precinct 1
☐ Precinct 2
☒ Precinct 3
☐ Precinct 4Fiscal and Personnel Summary |
Service Name |
- |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
- |
- |
- |
Non-Labor Expenditures |
- |
- |
- |
Total Incremental Expenditures |
- |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
- |
- |
- |
Additional Budget Requested |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
- |
- |
- |
Total Funding Sources |
- |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: 9/14/2021
Emergency/Disaster Recovery Note:
☒ Not an emergency, disaster recovery, or COVID-19 related item
☐ Emergency Item
☐ COVID-19 related Item
☐ Disaster Recovery related Item
Contact(s) name, title, department: Marcus Baskin, Recovery and Resiliency Division Manager, Harris County Engineering Department
Attachments (if applicable): N/A