Department: County Engineer
Department Head/Elected Official: John R. Blount, P.E., County Engineer
Regular or Supplemental RCA:
☒ Regular RCA
☐ Supplemental RCA
Type of Request: Authorization to Negotiate
Project ID (if applicable): 22035MF2B901
Vendor/Entity Legal Name (if applicable): Johnston, LLC
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval to negotiate with Johnston, LLC, for Professional Architectural and Engineering Services in connection with the renovation of 3 floors for 1111 Fannin, Precinct 1.
end
Background and Discussion:
Harris County recently purchased 1111 Fannin to be the new offices for HCED, HCFCD, and CSD. These 3 departments will occupy the majority of the building; however, some additional space is available for other departments to occupy.
Expected Impact:
The approval of this item will allow for a portion of some HC departments to occupy 1111 Fannin while vacating their existing space for other departments that are growing and need space for staff.
Alternative Options:
Alternative would be to not do the project and therefore, we would not have available space for other departments to locate their staff.
Alignment with Goal(s):
☐ Justice and Safety
☐ Economic Opportunity
☐ Housing
☐ Public Health
☐ Transportation
☐ Flooding
☐ Environment
☒ Governance and Customer Service
Prior Court Action (if any): N/A
Location:
Address (if applicable list below):
1111 Fannin
Houston, TX 77002
☒ Countywide
☒ Precinct 1
☐ Precinct 2
☐ Precinct 3
☐ Precinct 4Fiscal and Personnel Summary |
Service Name |
- |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
|
- |
- |
Non-Labor Expenditures |
- |
- |
- |
Total Incremental Expenditures |
|
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
CIP |
|
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
|
- |
- |
Additional Budget Requested |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
- |
- |
- |
Total Funding Sources |
|
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: 9/14/2021
Emergency/Disaster Recovery Note:
☒ Not an emergency, disaster recovery, or COVID-19 related item
☐ Emergency Item
☐ COVID-19 related Item
☐ Disaster Recovery related Item
Contact(s) name, title, department: Jacob Frazelle, Director, FPM
Attachments (if applicable): N/A