Department: County Engineer
Department Head/Elected Official: John R. Blount, P.E., County Engineer
Regular or Supplemental RCA:
☒ Regular RCA
☐ Supplemental RCA
Type of Request: Policy
Project ID (if applicable): UPIN 20102MF1EZ01
Vendor/Entity Legal Name (if applicable): Cobb, Fendley and Associates
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval of a study report prepared by Cobb, Fendley, and Associates for Kowis Street Reconstruction - Royal Pine to approx. 180’ E of Bentley Rd, Precinct 2.
end
Background and Discussion:
ATN and PSA was previously submitted to court to negotiate with and to start working with Cobb Fendley and Associates on the study for the Kowis Street Reconstruction - Royal Pine to approx. 180’ E of Bentley Rd project.
Expected Impact:
Roadway Reconstruction
Alternative Options: N/A
Alignment with Goal(s):
☐ Justice and Safety
☐ Economic Opportunity
☐ Housing
☐ Public Health
☒ Transportation
☐ Flooding
☐ Environment
☐ Governance and Customer ServicePrior Court Action (if any):
09/10/2019 - Authorization to Negotiate (ATN)
01/07/2020 - Professional Services Agreement (PSA)
Location:
Address (if applicable list below):
Kowis Street - Royal Pine to approx. 180’ E of Bentley Rd
☐ Countywide
☐ Precinct 1
☒ Precinct 2
☐ Precinct 3
☐ Precinct 4Fiscal and Personnel Summary |
Service Name |
- |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
- |
- |
- |
Non-Labor Expenditures |
- |
- |
- |
Total Incremental Expenditures |
- |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
- |
- |
- |
Additional Budget Requested |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
- |
- |
- |
Total Funding Sources |
- |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: September 14, 2021
Emergency/Disaster Recovery Note:
☒ Not an emergency, disaster recovery, or COVID-19 related item
☐ Emergency Item
☐ COVID-19 related Item
☐ Disaster Recovery related Item
Contact(s) name, title, department:
Amanda Marshall, P.E., Project Manager, HCED Phone: 713.274.3614
Email: amanda.marshall@eng.hctx.net
Attachments (if applicable):
Study Report