Department: Toll Road Authority
Department Head/Elected Official: Roberto Trevino, P.E., Executive Director
Regular or Supplemental RCA:
☒ Regular RCA
☐ Supplemental RCA
Type of Request: Public Necessity
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): N/A
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval to decree that the Hardy Toll Road Downtown Connector Project serves a public purpose and public necessity requiring that the Harris County Real Property Division be directed to acquire the identified two (2) tracts with a combined total acreage of less than 1.1 acres, using eminent domain if necessary (Precinct 1).
end
Background and Discussion:
In April 2018, Commissioners Court decreed public necessity of eight (8) tracts for the Hardy Toll Road Downtown Connector Project. The project is planned to extend the current Hardy Toll Road from its current terminus at IH 610 North into downtown Houston, and the solicitation for statements of qualifications for planning and conceptual design of the connector is anticipated to be issued by the end September 2021.
Parcel 8, the Union Pacific Railroad right-of-way (ROW), has been revised and authorization is being requested for Harris County Real Property Division to continue with necessary acquisitions as detailed in the attached Findings and Declarations.
A Temporary Construction Easement for Parcel 12TCE is also required to provide contractor access during construction.
Expected Impact:
These parcels are adjacent to the Union Pacific ROW and will provide access to the IH 69 corridor as well as allowing the future toll road to be constructed.
Alternative Options:
No other recommended solutions for this identified need.
Alignment with Goal(s):
☐ Justice and Safety
☐ Economic Opportunity
☐ Housing
☐ Public Health
☒ Transportation
☐ Flooding
☐ Environment
☐ Governance and Customer ServicePrior Court Action (if any): 04/10/2018, Item 1.d.1, Court authorization decreeing public necessity
Location:
Address (if applicable list below):
☐ Countywide
☒ Precinct 1
☐ Precinct 2
☐ Precinct 3
☐ Precinct 4Fiscal and Personnel Summary |
Service Name |
Engineering & Construction Services |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
- |
- |
- |
Non-Labor Expenditures |
- |
- |
- |
Total Incremental Expenditures |
- |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
TRA Capital Funds |
$ 579K |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
$ 579K |
- |
- |
Additional Budget Requested |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
- |
- |
- |
Total Funding Sources |
$ 579K |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: September 14, 2021
Emergency/Disaster Recovery Note:
☒ Not an emergency, disaster recovery, or COVID-19 related item
☐ Emergency Item
☐ COVID-19 related Item
☐ Disaster Recovery related Item
Contact(s) name, title, department: Nicole Stuttz, Assistant Director, Harris County Toll Road Authority
Attachments (if applicable): Parcel Documents