Department: Flood Control District
Department Head/Elected Official: Alan R. Black, P.E., Interim Executive Director
Regular or Supplemental RCA:
? Regular RCA
? Supplemental RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): K120-03-00-E001
Vendor/Entity Legal Name (if applicable): Harris County Water Control & Improvement District 110 and Harris County Municipal Utility District No. 249
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval of an interlocal agreement with Harris County Water Control & Improvement District No. 110 and Harris County Municipal Utility District No. 249, in the amount of $211,764, for a partnership project within the limits of these Districts in the Cypress Creek Watershed, Bond ID Z-02, Project ID K120-03-00-E001, Agreement No. 2020-108, Precinct 4.
end
Background and Discussion:
The project is located upstream of Cypresswood, along K120-30-00. Harris County Water Control & Improvement District 110 (WCID 110) and Harris County Municipal Utility District No. 249 (HC MUD 249) own and maintain adjacent existing detention basin with a common berm. WCID 110 and HC MUD 249 will excavate the common berm for additional volume to expand the existing basins. HCFCD's contribution is to fund 50 percent of the estimated project cost, inclusive of design and management costs. WCID 110 will design the facility, bid, award and manage construction.
Expected Impact:
The excavated detention basin will reduce water surface elevations along K120-03-00 upstream of Cypresswood.
Alternative Options:
No action will leave HC MUD 249 and WCID 110 with a shortfall in funding, which is necessary to complete the flood damage reduction project.
Alignment with Goal(s):
? Justice and Safety
? Economic Opportunity
? Housing
? Public Health
? Transportation
? Flooding
? Environment
? Governance and Customer Service
Prior Court Action (if any):
10/08/2019, [2.b], ATN
Lo...
Click here for full text