File #: 21-4769    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/6/2021 In control: Commissioners Court
On agenda: 9/14/2021 Final action: 9/14/2021
Title: Request for approval of change in contract with JT Vaughn Construction, LLC, Institute of Forensic Sciences - Renovations to Level 8, an addition of $5,571.00, Job No. 20/0219-4, Precinct 1.

Department: County Engineer

 

Department Head/Elected Official: John R. Blount, P.E., County Engineer

 

Regular or Supplemental RCA:

Regular RCA

Supplemental RCA

 

Type of Request: Contract - Amendment

 

Project ID (if applicable): 20035MF1JR01

Vendor/Entity Legal Name (if applicable): JT Vaughn Construction, LLC

MWDBE Participation (if applicable): N/A

 

Request Summary (Agenda Caption):

title

Request for approval of change in contract with JT Vaughn Construction, LLC, Institute of Forensic Sciences - Renovations to Level 8, an addition of $5,571.00, Job No. 20/0219-4, Precinct 1.

end

 

Background and Discussion:

 

 The renovation on Level 8 is the expansion of the Quality Management group with a break room, a multipurpose room expansion and a conference room.

This change in contract entails modifications to the upper cabinets in the break room and door closers at openings 8103 and 8501.

 

 

Expected Impact:

 

 Changes meet the operational needs to the end users. This proposed change in contract is within the approved project budget.

 

 

 

Alternative Options: N/A

 

 

 

Alignment with Goal(s):

Justice and Safety

Economic Opportunity

Housing

Public Health

Transportation

Flooding

Environment

Governance and Customer Service

 

Prior Court Action (if any):

10/13/2020, Agenda Item #19.d.8.g., Project Award

 

 

Location:

Address (if applicable list below):

1861 Old Spanish Trail

Houston, TX 77030

 

 

Countywide

Precinct 1

Precinct 2

Precinct 3

Precinct 4

 

Fiscal and Personnel Summary

Service Name

-

FY 21-22

Estimates

 

 

 

FY 22

Next 3 FYs

Incremental Expenditures

Labor Expenditures

-

-

-

Non-Labor Expenditures

-

-

-

Total Incremental Expenditures

-

-

-

Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify)

Existing Budget

Commercial Paper-

$5.571K-

-

-

 

-

-

-

-

 

-

-

-

-

Total Current Budget

-

-

-

Additional Budget Requested

-

-

-

-

 

-

-

-

-

 

-

-

-

-

Total Additional Budget Requested

-

-

-

Total Funding Sources

$5.571K-

-

-

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Implementation Date: 9/14/2021

 

Emergency/Disaster Recovery Note:

Not an emergency, disaster recovery, or COVID-19 related item

 

Emergency Item

COVID-19 related Item

Disaster Recovery related Item

 

Contact(s) name, title, department:

Trevor Wood, Manager of Construction Services, Engineering Department-Facilities and Property Maintenance

 

Attachments (if applicable):

County Auditor’s Form 1258B (Job No. 20/0219-4)