Department: County Engineer
Department Head/Elected Official: John R. Blount, P.E., County Engineer
Regular or Supplemental RCA:
☒ Regular RCA
☐ Supplemental RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 22103N301030006
Vendor/Entity Legal Name (if applicable): Cobb Fendley & Associates, Inc.
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval of an agreement with Cobb Fendley & Associates, Inc. in the amount of $1,099,650.30 for Professional Engineering Services for improvements to Peek Road Segment 3 from north of Stockdick School Road to north of Beckendorff Road, UPIN 22103N301030006, Precinct 3.
end
Background and Discussion:
The County engaged Cobb Fendley & Associates, Inc. in 2021, and now seeks Cobb Fendley & Associates, Inc. to facilitate the study and design of a standard four (4) lane concrete boulevard including bridge over South Mayde Creek (U101-00-00). The goal of studying and designing Peek Road Segment 3 from North of Stockdick School Road to North of Beckendorff Road is to replace the existing 2-lane asphalt roadway with a 4-lane concrete boulevard and improve mobility in the area. Cobb Fendley & Associates, Inc. is qualified to perform these professional services. The firm is registered with the Harris County Engineering Department Professional Services Registry.
Expected Impact:
The project will address current and future traffic volumes, reduce delays, and provide safe mobility for residents, pedestrians and drivers.
Alternative Options:
If no action is taken, the project may experience delays in improving mobility in the area.
Alignment with Goal(s):
☐ Justice and Safety
☐ Economic Opportunity
☐ Housing
☐ Public Health
☒ Transportation
☐ Flooding
☐ Environment
☐ Governance and Customer Service
Prior Court Action (if any):
04/13/2021; Cobb Fendley & Associates, Inc. Authorization to Negotiate request approved on court
Location:
Address (if applicable list below):
☐ Countywide
☐ Precinct 1
☐ Precinct 2
☒ Precinct 3
☐ Precinct 4
Fiscal and Personnel Summary |
Service Name |
- |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
- |
- |
- |
Non-Labor Expenditures |
- |
- |
- |
Total Incremental Expenditures |
- |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
Precinct 3- |
1.09M- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
- |
- |
- |
Additional Budget Requested |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
- |
- |
- |
Total Funding Sources |
$1.09M- |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: 9/14/2021
Emergency/Disaster Recovery Note:
☒ Not an emergency, disaster recovery, or COVID-19 related item
☐ Emergency Item
☐ COVID-19 related Item
☐ Disaster Recovery related Item
Contact(s) name, title, department:
Demetria Williams, CFM, ENV SP, Project Manager, Engineering Department
Demetria.Williams@eng.hctx.net, 713-274-3882
Attachments (if applicable): Agreement