Department: County Engineer
Department Head/Elected Official: John R. Blount, P.E., County Engineer
Regular or Supplemental RCA:
☒ Regular RCA
☐ Supplemental RCA
Type of Request: Contract - Award
Project ID (if applicable): 20101MF1F101
Vendor/Entity Legal Name (if applicable): Clark Condon Associates, Inc.
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval of an agreement with Clark Condon Associates, Inc. in the amount of $511,828.90 for Professional Landscape Architecture and Engineering Services for Boardwalk Renovation in Challenger 7 Park, Precinct 1.
end
Background and Discussion:
Provide professional services in connection for the Challenger 7 Park boardwalk renovation project near League City in Precinct 1. There is a TWPD grant approved for the master plan of Challenger 7.
Expected Impact:
To execute the masterplan and complete the study, design, and Bid phases of this project.
Alternative Options:
Authorization to negotiate with a different consultant.
Alignment with Goal(s):
☐ Justice and Safety
☐ Economic Opportunity
☐ Housing
☐ Public Health
☐ Transportation
☐ Flooding
☒ Environment
☐ Governance and Customer Service
Prior Court Action (if any): N/A
Location:
Address (if applicable list below):
2301 W. Nasa Pkwy. Webster, TX 77058
☐ Countywide
☒ Precinct 1
☐ Precinct 2
☐ Precinct 3
☐ Precinct 4
Fiscal and Personnel Summary |
Service Name |
-Landscape Architect |
FY 21-22 |
Estimates |
|
|
|
FY 22 |
Next 3 FYs |
Incremental Expenditures |
Labor Expenditures |
- |
- |
- |
Non-Labor Expenditures |
$512k- |
- |
- |
Total Incremental Expenditures |
- |
- |
- |
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify) |
Existing Budget |
- |
- |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Current Budget |
- |
- |
- |
Additional Budget Requested |
General Fund- |
$512k |
- |
- |
|
- |
- |
- |
- |
|
- |
- |
- |
- |
Total Additional Budget Requested |
- |
- |
- |
Total Funding Sources |
$512k- |
- |
- |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Implementation Date: 9/14/2021
Emergency/Disaster Recovery Note:
☒ Not an emergency, disaster recovery, or COVID-19 related item
☐ Emergency Item
☐ COVID-19 related Item
☐ Disaster Recovery related Item
Contact(s) name, title, department:
Grace Tsai, PE, Manager of Design Services, Engineering Department
Grace.tsai@eng.hctx.net, 713-274-3686
Attachments (if applicable): Agreement