To: Harris County Commissioners Court
Through: Russell A. Poppe, P.E., Executive Director, Harris County Flood Control District
prepared
Prepared By: Matthew K. Zeve, P.E., Deputy Executive Director, Harris County Flood Control District
Subject: New Bond Project Authorization
end
Project ID (If applicable]: P138-00-00-P001
Purpose and Request:
title:
Recommendation for authorization to initiate and proceed with a feasibility study for drainage improvements along HCFCD Unit P138-00-00. (Greens Bayou Watershed, Bond ID Z-03, Project ID P138-00-00-P001, Precincts 1, 2, and 4).
end
Background and Discussion:
HCFCD unit P138-00-00 is a tributary to Greens Bayou. The channel runs from around West Road and Veterans Memorial east to Greens Bayou near the Lauder stormwater detention basin. IH-45 and the Hardy Toll Road cross the channel. There is an opportunity to work and coordinate with TxDOT and HCTRA on improvements to P138-00-00 as part of drainage improvements to IH-45 and the Hardy Toll Road.
Fiscal Impact: There is no cost associated with this court item.
Fiscal Summary |
Expenditures |
FY 20-21 |
FY 21-22 Projected |
Future Years Projected [3 additional years] |
Service Impacted: 4.a.5 - Planning Services |
|
|
|
Existing Budget |
$0 |
$0 |
$0 |
Additional Appropriation Requested |
$0 |
$0 |
$0 |
Total Expenditures |
$0 |
$0 |
$0 |
Funding Sources |
$0 |
$0 |
$0 |
Existing Department Budget |
$0 |
$0 |
$0 |
Please Identify Funding Source (General Fund, PIC, Special Revenue, Grant, Etc.) |
$0 |
$0 |
$0 |
2018 HCFCD Bond Program - Z-02* |
$0 |
$0 |
$0 |
Total Sources |
$0 |
$0 |
$0 |
Alternatives The alternative is not complete this feasibility study.
Alignment with Strategic Objective:
SO1.1 Continuously plan CIP projects to improve conveyance capabilities of Harris County through addition of assets to District infrastructure and improving existing assets within the District’s existing infrastructure.
Attachments: Vicinity map