To: Harris County Commissioners Court
Through: Russell A. Poppe, P.E., Executive Director, Harris County Flood Control District
prepared
Prepared By: Matthew K. Zeve, P.E., Deputy Executive Director, Harris County Flood Control District
Subject: Change in Contract with Ragle, Inc.
end
Project ID (If applicable]: D100-00-00-B030
Purpose and Request:
title:
Recommendation for approval of Change in Contract No. 2 with Ragle, Inc., for the South Rice Avenue and Chimney Rock bridges, resulting in an increase of $15,508. (Brays Bayou Watershed, Bond ID C-11, Project ID D100-00-00-B030, Job No. 20/0347-02, Precinct 3).
end
Background and Discussion:
The purpose of this change in contract is adjust the planned and projected quantity needed for utility coordination and asphalt pavement removal. A power pole must be relocated out of the area of proposed pavement and additional funds are needed. The quantity for removal of existing asphalt pavement at South Rice was not included in the contract bid quantities. This results in a net increase of $15,508 to the contract with no additional days.
Fiscal Impact: The contract value increased by $15,508.
Fiscal Summary
Expenditures
FY 20-21
FY 21-22 Projected
Future Years Projected [3 additional years]
Service Impacted:
4.a.2 - Construction Services
Existing Budget
$0
$0
$0
Additional Appropriation Requested
$0
$0
$0
Total Expenditures
$0
$0
$0
Funding Sources
$0
$0
$0
Existing Department Budget
$0
$0
$0
Please Identify Funding Source (General Fund, PIC, Special Revenue, Grant, Etc.)
$0
$0
$0
2018 HCFCD Bond Program - C-11*
$0
$15,508
$0
Total Sources
$0
$15,508
$0
Alternatives:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.
Alignment with Strategic Objective:
SO1.1 - Continuously plan CIP projects ...
Click here for full text