Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County
Secondary Department: Choose an item.
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable):25104MF3VR01
Vendor/Entity Legal Name (if applicable): InfraTECH Engineers & Innovators, LLC
MWBE Contracted Goal (if applicable): 11.35%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with InfraTECH Engineers & Innovators, LLC., in the amount of $2,715,230.28 for Professional Engineering Services in connection with Sidewalk and Trail Program - 2025, UPIN 25104MF3VR01, Precinct 4, MWBE Contracted Goal: 11.35%.
end
Background and Discussion:
Office of the County Engineer (OCE) received a request from Precinct 4 to manage the study, design, and construction of the Sidewalk and Trail program within Precinct 4. Construction will improve connectivity and mobility of pedestrians at critical locations by installing a typical 6ft wide sidewalk.
Expected Impact:
To provide Precinct 4 with professional engineering study, design and construction services for the construction of the Sidewalk and Trail Program.
Alternative Options:
Without this project, the construction of the Sidewalk and Trail will not be realized as requested by Precinct 4.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiat...