Legislation Details

File #: 26-5496    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/12/2026 In control: Commissioners Court
On agenda: 8/25/2026 Final action: 8/25/2026
Title: Request for approval of a change in contract with Environmental Allies Inc., in connection with North Forest Subdivision Drainage Improvements 2018, adding 35 calendar days, with an addition in the amount of $27,712.32, Job No. 24/0359-2, Grant Fund, UPIN 19101MF16R01, Precinct 1, MWBE Contracted Goal: 29.74%, MWBE Current Participation: 32.52%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0359, UPIN 19101MF16R01.
Vendor/Entity Legal Name (if applicable): Environmental Allies Inc.

MWBE Contracted Goal (if applicable): 29.74%
MWBE Current Participation (if applicable): 32.52%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies Inc., in connection with North Forest Subdivision Drainage Improvements 2018, adding 35 calendar days, with an addition in the amount of $27,712.32, Job No. 24/0359-2, Grant Fund, UPIN 19101MF16R01, Precinct 1, MWBE Contracted Goal: 29.74%, MWBE Current Participation: 32.52%.
end

Background and Discussion:
The project includes an underground storm sewer system and a wet bottom detention basin. Project also include full-width roadway pavement reconstruction, sidewalk reconstruction and widening, and joint and crack cleaning and sealing throughout the North Forest Subdivision.

The change in contract includes the following:

The line items are adjusted to reconcile overrun, underrun quantities and add new line items to the project for completion of the proposed scope of work.

* The increase in quantities for existing line items 13, 15, 48, 106, 127, and 131 for an addition in the amount of $22,085.92.

* The decrease in quantities for existing line item 41 for a deduction in the amount of $154,834.42.

New Line Items:

* Add a new line Item 188 - Install of 18-inch Reinforced Concrete Pipe (RCP) for an addition in ...

Click here for full text