Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0307, UPIN 24208MF33D01
Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC
MWBE Contracted Goal (if applicable): 32.06%
MWBE Current Participation (if applicable): 9.24%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Intersection Improvement - Fry Road at Mound Road and Cypress North Houston Road at Barker Cypress Road - 2023, adding 2 calendar days, with an addition in the amount of $1,671.60, Job No. 24/0307-1, UPIN 24208MF33D01, Precinct 3, MWBE Contracted Goal: 32.06%, MWBE Current Participation: 9.24%.
end
Background and Discussion:
Project involves constructing of dual left turn lanes at both intersections. Upgrades to the traffic signals and investigate sight distance restrictions and operating conditions, striping, signage improvements and loop detectors. Changes include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes.
- Final Adjustments = $1,671.60
Change also include added (2) calendar days as follows:
- PCO-2 - Installation of SOD for all disturbed areas along medians 175 SY x $12.00 =$2100 -grant 1 additional day
- PCO-3 - Agree to pay 8" CEMENT STABILIZED SAND BEDDING BASE 1521.69 SY x $40.00 = $60,867.60 - grant 1 additional day
- PCO-4 - Items granted to be paid: 4" skips install/165 LF x $2.00=$330.00; 4" solid ...