Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 24035MF34X01
Vendor/Entity Legal Name (if applicable): LJA Engineering, Inc.
MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with LJA Engineering, Inc. in the amount of $230,020.48 for professional engineering services for two rebuild traffic signals with pedestrian related appurtenances at the intersections of Hopper Road at Bentley Road and Hopper Road at Foy Lane, UPIN 24035MF34X01, Precinct 2, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 0%.
end
Background and Discussion:
Traffic signals are rebuilt to improve the operation of an intersection and better facilitate pedestrian activities. As such, the consultant will be tasked with the signal design of the intersection to improve operations. The consultant will be tasked with evaluating pedestrian accessibility through the provision of crosswalks and associated median nose opening adjustments required to facilitate pedestrian activities.
Expected Impact:
Designing and constructing a traffic signal at this intersection will improve operations and better facilitate pedestrian activities.
Alternative Options:
This location currently operates using an existing traffic signal at the intersection. An alternative is to not rebuild the signal at the intersection, which will not provide additional operational and pedestrian benefits.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Ta...
Click here for full text