Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 26103ZE04C01
Vendor/Entity Legal Name (if applicable): Isani Consultants, L.P.
MWBE Contracted Goal (if applicable): 20%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Isani Consultants, L.P. in the amount of $230,086.50 for Professional Engineering Services in connection with Roadway Maintenance - Asphalt Package Cypress North Houston - 2027, UPIN 26103ZE04C01, Precinct 3, MWBE Contracted Goal: 20%.
end
Background and Discussion:
Precinct 3 is requesting the Office of the County Engineer to enter into an agreement for professional engineering services to provide design for Roadway Maintenance - Asphalt Package Cypress North Houston - 2027, covering the following road segments: 1. Cypress North Houston (RLN 3167321, 3167320, 3167323, and a portion of 3167322) from Barwood Bend Drive to East of Jones Road (1.84 miles). 2. Cypress North Houston (RLN 3167322, 3167301, 3167316, and 3167318) from Telge Road to Barwood Bend Drive (2.13 miles).
Expected Impact:
This agreement will allow the firm to proceed with design for the asphalt roadway project improvements.
Alternative Options:
The alternative is for the roadway to remain as-is, without improving the roadway conditions.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-ma...