Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 21103N306430001
Vendor/Entity Legal Name (if applicable): Walter P. Moore & Associates Inc.
MWDBE Contracted Goal (if applicable): 17.88%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Walter P. Moore & Associates Inc. in the amount of $114,543.50 for construction phase services for Detention Basin Enhancement Program - Cypress - 2021, UPIN 21103N306430001, Precinct 3, MWDBE Contracted Goal: 17.88%.
end
Background and Discussion:
Harris County desires to engage Walter P. Moore & Associates Inc. assist with construction phase services. The goal of the project is to reduce area flood risk by maximizing the detention volume prior to rain event.
Expected Impact:
The project intends to reduce area flood risk by maximizing the detention volume prior to rain event. The project will result in 119.4 additional ac-ft storage. The bidding and construction of this project was combined with the bidding and construction of the RRD K500 Detention Basin expansion project.
Alternative Options:
If no action is taken, the public may experience greater flood risk than if the action is taken.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
8/10/2021
42
Authorization to negotiate
4/26/2022
23
Professional Service Agreement
Location:
Address (if applicable): Cypress Park
Precinct(s): Precinct 3
Fiscal and Personnel Summary
Service Name
Professional Services
Current Fiscal Year Cost
A...
Click here for full text