Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 2410MF3KU01
Vendor/Entity Legal Name (if applicable): STOA International Architects, Inc. DBA, STOA Architects
MWBE Contracted Goal (if applicable): 20.26%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Personal Services Agreement
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with STOA International Architects, Inc., in the amount of $206,000.00, to provide Construction Documents needed for the construction of a new service shed and canopy at the Hockley Maintenance Service Center located at 28511 Old Washington Road, Precinct 4 Storage Facility - Hockley Service Center - 2004, UPIN 24104MF3KU01, MWBE Contracted Goal: 20.26%.
end
Background and Discussion:
STOA International Architects was approved as the prime consultant to begin negotiations for the design and construction of a 2,600 SF enclosed storage shed and an 8,160 SF pre-engineered metal building open canopy as well as a comprehensive site assessment to determine the most functional and strategic location for these new structures. The evaluations include a Topographical survey and a subsurface engineering utility survey, review of an existing geotechnical report, producing as-built drawings reflecting existing site conditions, cost estimates for recommended design and construction approach and emphasizing architectural design elements that support an efficient and cohesive operational environment for the end users.
Expected Impact:
The approval of this agreement would a...
Click here for full text