Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, PE
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): 27103I0ZWE01
Vendor/Entity Legal Name (if applicable): Lago Bello Municipal Utility District No. 1A of Harris County
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an Interlocal Agreement with Lago Bello Municipal Utility District No. 1A in connection with Proposed Settlers Creek Boulevard Waterline Extension, UPIN 27103I0ZWE01, Precinct 3.
end
Background and Discussion:
The proposed Settlers Creek Boulevard Waterline Extension project aims to expand the existing water distribution system to support current and future development in the area. The project involves extending waterline infrastructure along Settlers Creek Boulevard to improve service availability, system reliability, and capacity while accommodating anticipated growth and community needs.
Expected Impact:
The proposed Settlers Creek Boulevard Waterline Extension is expected to improve water service reliability and availability for nearby properties and future developments. The project may increase water system capacity, support residential and commercial growth, and enhance infrastructure connectivity. Construction may cause temporary traffic disruptions, noise, and localized access restrictions.
Alternative Options: N/A
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A