Title: Request for approval to execute an Interlocal Agreement with Harris County Municipal District No. 304 to design and construct improvements for 6-foot sidewalks and drainage flumes along TC Jester Boulevard within the District and all related appurtenances, UPIN 24101MF3FR01, Precinct 1.
Attachments: 1. 26-5865-ILA-24101MF3FR01-Sidewalk-MUD304-P1-9.17.26-.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

Project ID (if applicable): UPIN 24101MF3FR01
Vendor/Entity Legal Name (if applicable): Harris County Municipal District No. 304

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an Interlocal Agreement with Harris County Municipal District No. 304 to design and construct improvements for 6-foot sidewalks and drainage flumes along TC Jester Boulevard within the District and all related appurtenances, UPIN 24101MF3FR01, Precinct 1.
end

Background and Discussion:
As part of the project, tie proposed sidewalks to existing sidewalk trails within the District property. The District will maintain the sidewalk constructed by Harris County within the District property.

Expected Impact:
Provide safer pedestrian access to the existing District trails.

Alternative Options:
No alternative options. If not approved, there will be no sidewalk connection to the District trails.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: G: Expand and optimize multimodal transportation options.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): G1: Expand pedestrian and cyclist infrastructure on County-managed roads,
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4):...