Legislation Details

File #: 24-5169    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/15/2024 In control: Commissioners Court
On agenda: 8/27/2024 Final action: 8/27/2024
Title: Request for approval of a change in contract with NBG Constructors, Inc., in connection with final construction of Bridge Replacement - Pedestrian Bridge - P152-00-00, adding 40 calendar days, with an addition in the amount of $8,242.00, Job No. 23/0001-1, UPIN 19104M23F502, Precinct 1, MWDBE Contracted Goal: 12%, MWDBE Current Participation: 18.33%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0001, UPIN 19104M23F502
Vendor/Entity Legal Name (if applicable): NBG Constructors, Inc.

MWDBE Contracted Goal (if applicable): 12%
MWDBE Current Participation (if applicable): 18.33%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with NBG Constructors, Inc., in connection with final construction of Bridge Replacement - Pedestrian Bridge - P152-00-00, adding 40 calendar days, with an addition in the amount of $8,242.00, Job No. 23/0001-1, UPIN 19104M23F502, Precinct 1, MWDBE Contracted Goal: 12%, MWDBE Current Participation: 18.33%.
end

Background and Discussion:
Project includes the demolition and replacement of the existing pedestrian bridge with a 107' prefabricated bridge and 295 LF of asphalt trail extensions to Spanish Oak.

This change in contracts includes:
Additions:
(PCO-1) Item #17 - Fold Down Bollard - Adding bollard to bid items. ($2,512.00).

(PCO-1) Item #18 - Furnish and Install Hydro Mulch - Adding hydro mulch to bid items to meet HCFCD standards for turf establishment. ($2,530.00).

(PCO-1) Item #19 - Furnish and Install Type 3 Barricade - Adding Type 3 barricade to bid items as called out in the plans. ($3,496.00).

(PCO-2) Adding 40 days due to the long lead time from the time the bridge shop drawing can be approved to the time the bridge was delivered.

Deductions:
(PCO-3) Item #6 - Emulsified Asphalt (Prime Coat) (-$36.00).

(PCO-3) Item #7 - Dense-Graded Hot-mix asphalt base course (-$260.00)

Expected Impact:
Change allows the contractor to be compensated for the items which were in the plan but missed in the bid tab.

Alternative Options:
Reduce the original scope of ...

Click here for full text