Legislation Details

File #: 24-6090    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/23/2024 In control: Commissioners Court
On agenda: 10/8/2024 Final action: 10/8/2024
Title: Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements Project, adding 30 calendar days, Job No. 23/0278-4, Bond Fund, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 26.45%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19102MF17801; Job No: 23/0278
Vendor/Entity Legal Name (if applicable): CE Barker Ltd.

MWDBE Contracted Goal (if applicable): 26%
MWDBE Current Participation (if applicable): 26.45%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements Project, adding 30 calendar days, Job No. 23/0278-4, Bond Fund, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 26.45%.
end

Background and Discussion:
Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements project is in the Northeast area of Harris County, east of FM 2100 and north of FM 1942. The scope of this project includes regrading roadside ditches, replace undersized driveway culverts, removal and replacement of driveways, road replacement in certain sections and construction of a dry bottom detention basin with pump station on the northeast corner of the subdivision, south of East Broussard.

The change in the contract is needed to add additional days. Below is the description of the changes:

Due to a conflict with non-operational water shutoff valves and scheduling issues, MUD was unable to shut off the water as required. This situation has delayed the contractor's ability to perform the wet connections needed to complete the utility relocations, ditch grading and the driveways for an additional 30 days.

This results in a net change in the amount of $0.00 and 30 calendar days.

Expected Impact:
This project seeks to reduce flooding and strengthe...

Click here for full text