Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No: 21/0301, UPIN 22101MF2C901
Vendor/Entity Legal Name (if applicable): J Rivas Construction, LLC
MWDBE Contracted Goal (if applicable): 14%
MWDBE Current Participation (if applicable): 92.77%
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with J Rivas Construction, LLC in connection with final On-Call - Maintenance - Storm Drain Repair, Precinct 1 -2021, with a deduction in the amount of $59,025.45, Job No. 21/0301-1, UPIN 22101MF2C901, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 92.77%.
end
Background and Discussion:
This On-Call Contract provides storm drain services of areas to Precinct 1, with a deduction of $59,025.45 to the Final PCO. The improvements are to provide storm drain repair to selected streets. Change allows unused funds to be returned to the Precinct and allow the Contractor to be compensated for the actual work completed on the project.
Expected Impact:
Change allows unused funds to be returned to the Precinct and allow the Contractor to be compensated for the actual work completed on the project.
Alternative Options:
Maintain the original scope of the project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
06/06/2023
23-3177
Contract Renewal
Location:
Address (if applicable):
Precinct(s): Precinct 1
Fiscal and Personnel Summary
Service Name
Engineering
Current Fiscal Year Cost
Annual Fiscal Cost
Labor
Non-Labor
Total
Recurring Expenses
Funding Sources
Existin...