Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0019
Vendor/Entity Legal Name (if applicable): GLM Contracting, Inc.
MWDBE Contracted Goal (if applicable): 19%
MWDBE Current Participation (if applicable): 20.98%
Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption): 
title
Request for approval of a change in contract with GLM Contracting, Inc., in connection with final On-Call - Construction - General Civil - 2021, with an addition in the amount of $101,392.50, Job No. 22/0019-1, UPIN 22103MF2E401, Precinct 3, MWDBE Contracted Goal: 19%, MWDBE Current Participation: 20.98%. 
end
Background and Discussion: 
Project includes General Civil On-Call Ramps and Paving Improvements.
Change includes reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes. 
? Major reduced items include; remove existing concrete driveways, paving, sidewalks, curbs, ramps, median
   nosing, etc. (All thicknesses). 
? Major increased items include; reinforced concrete pavement (6" depth), concrete sidewalk (4 1/2 thickness)
   - less than or equal to 100 LF continuous, 6" thick reinforced concrete driveway with high early strength
   concrete (minimum bid - $150/SY) 
? Repair of existing underground drainage box = $14,700.00 
? Removing the broken wall at the bayou bridge = $6,300.00 ? Build a 20 ft long by 3 ft high wall over the bridge
   = $15,600.00 
? Work performed on the parapet wall on Louetta bridge = $7,900.00 
? Concrete slab at the Meyer Park Water Tank = $58,727.00
Expected Impact: 
Change allows unused funds to be returned to the Precinct and allow the Contractor to be compensated for the actual work completed on the project.