Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Grant - Amendment
Project ID (if applicable): Z100-00-00-Y100
Vendor/Entity Legal Name (if applicable): United States Department of Agriculture/Natural Resources Conservation Service
MWBE Contracted Goal (if applicable):
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): 0%
Justification for 0% Grant Indirect Costs Rate (if applicable): HCFCD, HCTRA, HHS
Request Summary (Agenda Caption):
title
Request by the Flood Control District for approval to accept an amendment to an agreement with the United States Department of Agriculture/Natural Resources Conservation Service to extend the grant end date to December 31, 2026, for the Emergency Watershed Protection Program (Project ID Z100-00-00-Y100, Countywide).
end
Background and Discussion:
It is recommended that the Flood Control District be authorized to accept Amendment No. 1 to USDA NRCS Emergency Watershed Protection Program Cooperative Agreement No. NR267442XXXXC003 for Hurricane Beryl debris removal. The amendment extends the current period of performance by 92 calendar days, from September 30, 2026, through December 31, 2026, with no change in funding. The extension applies to NRCS Project No. 5118 and the Damage Survey Reports identified in the executed amendment.
Expected Impact:
Acceptance of the amendment will provide the Flood Control District additional time to complete the remaining Hurricane Beryl debris-removal work and prepare the project for closeout in accordance with NRCS requirements. The Flood Control District will continue to use its resources and applicable contractors and consultants to complete the work and administer ...