Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN - 24035MF3HP01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Houston Electric, LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy Houston Electric, LLC and authorize the County Auditor to pay monthly bills for 10302 ½ Veterans Memorial Drive, Houston, Texas 77038 for electrical power serving a traffic signal, Veterans Memorial Drive at Frick Road - FY23-24, UPIN 24035MF3HP01, Precinct 2.
end
Background and Discussion:
Rebuilding a traffic signal at the intersection of Veterans Memorial Drive at Frick Road is a project that aims to enhanced traffic movements at the existing intersection. The service outlet location statement is needed to establish electrical service from CenterPoint Energy Houston Electric, LLC to power the traffic signal.
Expected Impact:
Approval of the service outlet location statement will allow CenterPoint Energy Houston Electric, LLC to provide electrical service to the traffic signal, which is needed to enhance operations at the intersection Veterans Memorial Drive at Frick Road.
Alternative Options:
All traffic signals require a power source, which is typically obtained through CenterPoint Energy Houston Electric, LLC. Alternative options are to place a generator, which is no...