Harris County Commissioners Court
Request for Court Action
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Termination
Project ID (if applicable): UPIN 19102MF12U01
Vendor/Entity Legal Name (if applicable): Ward, Getz & Associates, PLLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a Mutual Termination Agreement with Ward, Getz & Associates, PLLC in connection with Sterling Forest Subdivision Drainage Improvements - 2018 (Phase 2), UPIN 19102MF12U01, Precinct 2.
end
Background and Discussion:
The professional services contract was originally executed on 12/01/2020 with Ward, Getz and Associates, PLLC. The project has been mutually agreed upon for termination. UPIN 19102MF12U01, Precinct 2
Expected Impact:
As this is a mutual termination agreement, there will be no additional cost to Harris County to terminate the agreement.
Alternative Options:
No alternative option. Both parties agree to mutually terminate the agreement.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health X Transportation X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
12/01/2020
1.g.2
Contract Agreement
Location:
Address (if applicable): Sterling Forest Subdivision Precinct(s): Precinct 2
Fiscal and Personnel Summary
Service Name
Current Fiscal Year Cost
Annual Fiscal Cost
Labor
Non-Labor
Total
Recurring Expenses
Funding Sources
Existing Budget
Choose an item.
$
$
$
$