Harris County Logo
File #: 24-1536    Version: 1 Name:
Type: Negotiation Status: Passed
File created: 3/13/2024 In control: Commissioners Court
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Request for approval to negotiate with Diaz Engineering LLC. for Professional Engineering Services in connection with a Drainage Study - Oakland Street Pipeline Crossing, UPIN 25102MF3D201, Precinct 2.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Negotiation

Project ID (if applicable): 25102MF3D201
Vendor/Entity Legal Name (if applicable): Diaz Engineering LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to negotiate with Diaz Engineering LLC. for Professional Engineering Services in connection with a Drainage Study - Oakland Street Pipeline Crossing, UPIN 25102MF3D201, Precinct 2.
end

Background and Discussion:
This request will allow Harris County to start negotiations with Diaz Engineering LLC to provide drainage assessments and recommendations at the 200 block of Oakland Street. Existing pipeline crossings in the area do not allow for ditches to be provided.

Expected Impact:
The investigation will provide design recommendations to address drainage deficiencies in the area.

Alternative Options:
If no action is taken, the project may experience delays in improving drainage in the area due to the lack of maintenance.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken


None

Location:
Address (if applicable): 200 Oakland St, Baytown, TX 77520
Precinct(s): Precinct 2

Fiscal and Personnel Summary
Service Name
Engineering


Current Fiscal Year Cost
Annual Fiscal Cost

Labor
Non-Labor
Total
Recurring Expenses
Funding Sources

Existing Budget




Choose an item.
$
$
$
$
Choose an item.
$
$
$
$
Choose an item.
$
$
$
$
Total Current Budget
$
$
$
$
Additional Budget Request (Requires Fiscal Review Request Form)

Choose an item.
$
$
$
$
Choose an item.
...

Click here for full text