File #: 25-4548    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/21/2025 In control: Commissioners Court
On agenda: 8/7/2025 Final action: 8/7/2025
Title: Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, adding 165 calendar days, with an addition in the amount of $129,743.13, Job No. 22/0461-8, UPIN 19101MF0XV01, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 38.76%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0461, UPIN 19101MF0XV01
Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.

MWBE Contracted Goal (if applicable): 25%
MWBE Current Participation (if applicable): 38.76%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, adding 165 calendar days, with an addition in the amount of $129,743.13, Job No. 22/0461-8, UPIN 19101MF0XV01, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 38.76%.
end

Background and Discussion:
This project includes the construction of four 11-foot-wide concrete pavement with a 24-foot median, and 8-foot-wide sidewalk along both sides West Gulf Bank Road from Interstate 45 Freeway to Airline Drive. It also includes the drainage improvements.

The change order includes the following:
- Due to a work conflict, the bus pad at the northeast corner of the Airline intersection had to be removed and reinstalled. Precinct 2 directed Harris County to proceed with full removal and replacement. The Engineer of Record provided recommendations to minimize the impact on the newly constructed bus pad while ensuring proper gutter line construction. This change order will add 2 days and additional cost of $8,031.19 to the contract.
- To address drainage concerns at Station 146+70LT, where the proposed sidewalk would block water o...