Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0408, UPIN 19102MF15W01
Vendor/Entity Legal Name (if applicable): Precise Services Inc.
MWBE Contracted Goal (if applicable): 22.81%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services Inc., in connection with final construction of Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, with an addition in the amount of $888,309.23, Job No. 24/0408-3, Infrastructure Fund, UPIN 19102MF15W01, Precinct 2, MWBE Contracted Goal: 22.81%, MWBE Current Participation: 100%.
end
Background and Discussion:
This project entails the construction of storm sewer drainage to convey drainage in the Cedar Bayou Park East and West Subdivision from Sjolander Road to Bayou Boulevard.
The change in contract includes the following:
The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.
* The increase of quantities on overrun line item numbers 09, 013, 014, 022, 025, 027, 047, 049, 057, 062, 063, 071, 077, 090, 096, 129, and 130 for an addition in the amount of $1,073,117.78.
* The decrease of quantities on underrun line item numbers 15, 016A, 028, 029, 048, 064, 065, 092, 094, 097, 098, 099, 102, 103, 105, 108, 109, 110, 111, 112A, 113, 114, 115, 116, 118, 121, 123, 132, and 133 for a deduction in the amount of $184,808.55.
The abov...